B.C.A. (Semester VI) (CGPA) Examination, 2017
SOFTWARE PROJECT MANAGEMENT
Day Date: Tuesday, 18-04-2017 Max. Marks: 70
Time: 10.30 AM to 01.00 PM
N.B. Q.1 and Q.7 are compulsory.
Attempt any two questions from Q. 3 and 4.
Attempt any one question from Q. 5 and 6.
Figures to the right indicate full marks.
Q.1 Choose correct alternatives: 07
The return on investment also known as
Accounting rate of return Accounting return
Audit rate of return Back investment
overall responsibility for setting, monitoring and
modifying objectives.
Project steering committee Designer
Developer Analyst
DSDM stands for
Dynamic Study Development Method
Diamond System Development Method
Dynamic System Development Method
Dynamic System Deployed Method
The collection of projects that an organization undertaken
within a particular planning cycle is sometimes referred to as
a
Portfolio Document file Plan file Project file
is also known as once-through model.
V-Process Rapid Application Mode
Waterfall Both a and b
the simplest and oldest techniques for tracking
project progress.
Slip Chart Gantt Chart Flow Chart Ball Chart
Which of the following is/are considered stakeholder in the
software process?
Customer
Internal to the project team
External to the project team
All of the above
Page 1 of 2
SLR-U 34
Q.1 State True or False: 07
The payback period is the time taken to break even or pay
back the initial investment.
Software quality assurance is an umbrella activity.
Software project planning is task, it is performed before the
production of software actually starts.
PERT stands for Program Entry and Review Technique.
Quality planning is the process of developing a quality plan
for project.
CPM stands for clean path method.
The forward pass is carried out to calculate the earliest dates
on which each activity may be started and completed.
Q.2 What is cash flow forecasting? 07
Where are estimates done of software project? 07
Q.3 Explain the Plans, Methods and Methodologies. 07
Explain the spiral model in details. 07
Q.4 Explain setting objectives and goals of project. 07
Explain the risk planning in details. 07
Q.5 Explain the step wise project planning in details. 07
Explain the COCOMO model in details. 07
Q.6 What are the activities covered by Software Project
Management?
07
What is incremental delivery approach of project? Explain with
advantages and disadvantages.
07
Q.7 Write short notes on (Any four) 14
Grant Chart
Software Quality Measures
Leadership
V-Process Model
The forward pass and backward pass


Subjects

  • advance programming in c
  • advanced java – i
  • advanced java – ii
  • advanced programming in ‘c’
  • advanced web technology
  • basics of ‘c’ programming
  • business communication
  • business statistics
  • communication skills
  • computer graphics
  • computer oriented statistics
  • core java
  • cyber laws and security control
  • data structure using ‘c’
  • data structures using ‘c’
  • data warehouse and data mining
  • database management system
  • dbms with oracle
  • development of human skills
  • digital electronics
  • discrete mathematics
  • e-commerce
  • e-governance
  • financial accounting with tally
  • financial management
  • fundamentals of computer
  • fundamentals of financial accounting
  • introduction to data mining & warehousing
  • introduction to information technology
  • linux and shell programming
  • management information system
  • networking & data communication
  • networking and data communication
  • object oriented programming with c++
  • oop with c++
  • operating system
  • operations research
  • operting system
  • procedural programming through ‘c’
  • python
  • rdbms with oracle
  • software engineering
  • software project management
  • software testing
  • theory of computation
  • visual programming
  • web technology
  • web technology – ii
  • web technology – iii