B.C.A. (Semester VI) Examination Oct/Nov-2017
SOFTWARE PROJECT MANAGEMENT
Day Date: Wednesday, 15-11-2017 Max. Marks: 80
Time: 10.30 AM to 01.30 PM
Instructions: Q.1 and Q.7 are compulsory.
Attempt any two questions from Q. 3 and 4.
Attempt any one question from Q. 5 and 6.
Figures to the right indicate full marks.
Q.1 Choose the correct alternatives: 08
has overall responsibility for setting, monitoring and
modifying objectives.
Developer Project steering committee
Designer Manager
WBS stands for
Worked Break Structure Work Breakdown Structure
Working Break System Work Basic System
The collection of projects that an organization undertaken within a
particular planning cycle is sometimes referred to as a
Document Project file
Plan file Portfolio
pass is carried out to calculate the earliest dates on which
each activity may be started and completed.
The backward pass The forward pass
The back-work pass Both b and c
Which of these software characteristics are used to determine the scope
of a software project?
Only performance
Only Context
Only Functional
Information objectives, function, performance
model is also known as once-through model..
Waterfall V-Process
RAD Both a and c
CPM stands for
Critical Path Method Critical Program Method
Complex Path Method Combine Path Method
Booch suggests that there are two levels of development the
process and the process.
Macro, micro Minimum, maximum
Min, max Main, sub
Page 2 of 2
SLR-CD-28
Q.1 State whether True or False 08
Software project management begins with a set of activities that are
collectively called Project Planning.
SSADM stand for structured system analysis and design
Stakeholders are peoples who have an interest in the project.
Elapsed time is the time between the start and end of a task.
Gantt chart is not simplest and oldest technique for tracking project
progress.
The waterfall model begins with feasibility study.
Bottom-up estimating methods can be generally divided into bottom-up
and top-down approaches.
RAD stand for rapid application development.
Q.2 What is risk management? Explain the planning in details. 06
Explain the Oldham-Hackman job characteristics model. 06
What is management? 04
Q.3 Explain V-Process model in details. 06
What are the activities covered by software project management? 06
What is Requirements Specification? 04
Q.4 Where are estimates done of software project? 06
Explain Plans, methods and methodologies in details. 06
Explain the function points Mark II. 04
Q.5 Explain cost benefit evaluation techniques in details. 08
What is software quality? Explain its practical measures. 08
Q.6 Explain the step wise project planning in details. 08
Explain the forward pass and backward pass in details. 08
Q.7 Note on (any four) 16
Setting Objectives and Goals of project
Stakeholders
Spiral Model
Cash flow forecasting
Motivation
SOFTWARE PROJECT MANAGEMENT
Day Date: Wednesday, 15-11-2017 Max. Marks: 80
Time: 10.30 AM to 01.30 PM
Instructions: Q.1 and Q.7 are compulsory.
Attempt any two questions from Q. 3 and 4.
Attempt any one question from Q. 5 and 6.
Figures to the right indicate full marks.
Q.1 Choose the correct alternatives: 08
has overall responsibility for setting, monitoring and
modifying objectives.
Developer Project steering committee
Designer Manager
WBS stands for
Worked Break Structure Work Breakdown Structure
Working Break System Work Basic System
The collection of projects that an organization undertaken within a
particular planning cycle is sometimes referred to as a
Document Project file
Plan file Portfolio
pass is carried out to calculate the earliest dates on which
each activity may be started and completed.
The backward pass The forward pass
The back-work pass Both b and c
Which of these software characteristics are used to determine the scope
of a software project?
Only performance
Only Context
Only Functional
Information objectives, function, performance
model is also known as once-through model..
Waterfall V-Process
RAD Both a and c
CPM stands for
Critical Path Method Critical Program Method
Complex Path Method Combine Path Method
Booch suggests that there are two levels of development the
process and the process.
Macro, micro Minimum, maximum
Min, max Main, sub
Page 2 of 2
SLR-CD-28
Q.1 State whether True or False 08
Software project management begins with a set of activities that are
collectively called Project Planning.
SSADM stand for structured system analysis and design
Stakeholders are peoples who have an interest in the project.
Elapsed time is the time between the start and end of a task.
Gantt chart is not simplest and oldest technique for tracking project
progress.
The waterfall model begins with feasibility study.
Bottom-up estimating methods can be generally divided into bottom-up
and top-down approaches.
RAD stand for rapid application development.
Q.2 What is risk management? Explain the planning in details. 06
Explain the Oldham-Hackman job characteristics model. 06
What is management? 04
Q.3 Explain V-Process model in details. 06
What are the activities covered by software project management? 06
What is Requirements Specification? 04
Q.4 Where are estimates done of software project? 06
Explain Plans, methods and methodologies in details. 06
Explain the function points Mark II. 04
Q.5 Explain cost benefit evaluation techniques in details. 08
What is software quality? Explain its practical measures. 08
Q.6 Explain the step wise project planning in details. 08
Explain the forward pass and backward pass in details. 08
Q.7 Note on (any four) 16
Setting Objectives and Goals of project
Stakeholders
Spiral Model
Cash flow forecasting
Motivation
Other Question Papers
Subjects
- advance programming in c
- advanced java – i
- advanced java – ii
- advanced programming in ‘c’
- advanced web technology
- basics of ‘c’ programming
- business communication
- business statistics
- communication skills
- computer graphics
- computer oriented statistics
- core java
- cyber laws and security control
- data structure using ‘c’
- data structures using ‘c’
- data warehouse and data mining
- database management system
- dbms with oracle
- development of human skills
- digital electronics
- discrete mathematics
- e-commerce
- e-governance
- financial accounting with tally
- financial management
- fundamentals of computer
- fundamentals of financial accounting
- introduction to data mining & warehousing
- introduction to information technology
- linux and shell programming
- management information system
- networking & data communication
- networking and data communication
- object oriented programming with c++
- oop with c++
- operating system
- operations research
- operting system
- procedural programming through ‘c’
- python
- rdbms with oracle
- software engineering
- software project management
- software testing
- theory of computation
- visual programming
- web technology
- web technology – ii
- web technology – iii