Exam Details
Subject | software project management | |
Paper | ||
Exam / Course | b.c.a | |
Department | ||
Organization | solapur university | |
Position | ||
Exam Date | November, 2017 | |
City, State | maharashtra, solapur |
Question Paper
B.C.A. (Semester VI) (CGPA) Examination Oct/Nov-2017
SOFTWARE PROJECT MANAGEMENT
Day Date: Wednesday, 15-11-2017 Max. Marks: 70
Time: 10.30 AM to 01.00 PM
Instructions: Q.1 and Q.7 are compulsory.
Attempt any two questions from Q. 3 and 4.
Attempt any one question from Q. 5 and 6.
Figures to the right indicate full marks.
Q.1 Choose the single correct alternatives: 14
A Plan takes and converts it to real Activities.
Methodology Method
Activity Time
The ISO 9126 sets the standard for
Software Processes Project Progress
Software Planning Software Quality
Steps to will need to be repeated for each activity in the
project.
4,8 7,9
5,8 2,4
is a working model of one or more aspects of the projected system.
Evolutionary approach Incremental delivery
Conceptual Integrity Prototype
Dummy activities are shown with lines on the network
diagram
Dashed Lines Dotted Lines
Double line Arrow lines
Effort (System Size) X (Productivity rate) is the formula to calculate efforts
in
Function points KLOC
Full Function Points Cost
RAG Reporting is an approach to
Analyzing Data Splitting Data
Collection Data Separating Data
COCOMO is
Construction Cosmic Code Cosmic Consortium Model
Constructive Cost Model Cognitive Cost Modeling
is are the Objective/s of Activity Planning
Feasibility Assessment Coordination
A and b None of these
10) is the method of improving motivation.
Providing Feedback Stress
Interview Skill Variety
Page 2 of 2
SLR-CD-24
11) Risk analysis and Prioritization is the phase in Risk planning
1st 3rd
2nd None of these
12) Backward pass means
Calculating latest date to start and end activity
Calculating dates to start and end activity time
Calculating time period to start and end activity
Calculating end date of an activity
13) is one of the visualizing Progress Method
Graph Pi Charts
The Timeline Slip chart
14) PERT means
Process Evaluation Review Technique
Program Evaluation Review Technique
Payback Evaluation Reframing Technique
Periodical Evaluation and Review Technique
Q.2 Write the answer of the following (any 14
Explain Plan, Method And Methodology with proper examples.
What is Contract management? Explain types of Contracts.
Explain Expert judgment and Estimation by Analogy.
Q.3 Write the answer of the following (any 14
What is an Activity? Explain Objectives of Activity Planning.
What is Organization behavior? Explain Motivation and Selecting right
persons for job.
Write a note on Identifying the critical path.
Q.4 Write the answer of the following (any 14
Explain and differentiate between Technical and Strategic Assessment
Explain different ways of visualizing progress.
Explain Waterfall Process Model.
Q.5 Write the answer of the following 14
Explain techniques to enhance software quality.
Explain Oldham Hackman Job Characteristics Model.
Q.6 Write the answer of the following 14
Explain Project planning steps with suitable diagram
Explain Risk Planning and controlling with proper example.
Q.7 Write short notes on the following (Any two) 14
Forward and Backward Pass
Resource Allocation
Process Model Selection
SOFTWARE PROJECT MANAGEMENT
Day Date: Wednesday, 15-11-2017 Max. Marks: 70
Time: 10.30 AM to 01.00 PM
Instructions: Q.1 and Q.7 are compulsory.
Attempt any two questions from Q. 3 and 4.
Attempt any one question from Q. 5 and 6.
Figures to the right indicate full marks.
Q.1 Choose the single correct alternatives: 14
A Plan takes and converts it to real Activities.
Methodology Method
Activity Time
The ISO 9126 sets the standard for
Software Processes Project Progress
Software Planning Software Quality
Steps to will need to be repeated for each activity in the
project.
4,8 7,9
5,8 2,4
is a working model of one or more aspects of the projected system.
Evolutionary approach Incremental delivery
Conceptual Integrity Prototype
Dummy activities are shown with lines on the network
diagram
Dashed Lines Dotted Lines
Double line Arrow lines
Effort (System Size) X (Productivity rate) is the formula to calculate efforts
in
Function points KLOC
Full Function Points Cost
RAG Reporting is an approach to
Analyzing Data Splitting Data
Collection Data Separating Data
COCOMO is
Construction Cosmic Code Cosmic Consortium Model
Constructive Cost Model Cognitive Cost Modeling
is are the Objective/s of Activity Planning
Feasibility Assessment Coordination
A and b None of these
10) is the method of improving motivation.
Providing Feedback Stress
Interview Skill Variety
Page 2 of 2
SLR-CD-24
11) Risk analysis and Prioritization is the phase in Risk planning
1st 3rd
2nd None of these
12) Backward pass means
Calculating latest date to start and end activity
Calculating dates to start and end activity time
Calculating time period to start and end activity
Calculating end date of an activity
13) is one of the visualizing Progress Method
Graph Pi Charts
The Timeline Slip chart
14) PERT means
Process Evaluation Review Technique
Program Evaluation Review Technique
Payback Evaluation Reframing Technique
Periodical Evaluation and Review Technique
Q.2 Write the answer of the following (any 14
Explain Plan, Method And Methodology with proper examples.
What is Contract management? Explain types of Contracts.
Explain Expert judgment and Estimation by Analogy.
Q.3 Write the answer of the following (any 14
What is an Activity? Explain Objectives of Activity Planning.
What is Organization behavior? Explain Motivation and Selecting right
persons for job.
Write a note on Identifying the critical path.
Q.4 Write the answer of the following (any 14
Explain and differentiate between Technical and Strategic Assessment
Explain different ways of visualizing progress.
Explain Waterfall Process Model.
Q.5 Write the answer of the following 14
Explain techniques to enhance software quality.
Explain Oldham Hackman Job Characteristics Model.
Q.6 Write the answer of the following 14
Explain Project planning steps with suitable diagram
Explain Risk Planning and controlling with proper example.
Q.7 Write short notes on the following (Any two) 14
Forward and Backward Pass
Resource Allocation
Process Model Selection
Other Question Papers
Subjects
- advance programming in c
- advanced java – i
- advanced java – ii
- advanced programming in ‘c’
- advanced web technology
- basics of ‘c’ programming
- business communication
- business statistics
- communication skills
- computer graphics
- computer oriented statistics
- core java
- cyber laws and security control
- data structure using ‘c’
- data structures using ‘c’
- data warehouse and data mining
- database management system
- dbms with oracle
- development of human skills
- digital electronics
- discrete mathematics
- e-commerce
- e-governance
- financial accounting with tally
- financial management
- fundamentals of computer
- fundamentals of financial accounting
- introduction to data mining & warehousing
- introduction to information technology
- linux and shell programming
- management information system
- networking & data communication
- networking and data communication
- object oriented programming with c++
- oop with c++
- operating system
- operations research
- operting system
- procedural programming through ‘c’
- python
- rdbms with oracle
- software engineering
- software project management
- software testing
- theory of computation
- visual programming
- web technology
- web technology – ii
- web technology – iii