Exam Details

Subject construction management and entrepreneurship
Paper
Exam / Course b.arch
Department
Organization Visvesvaraya Technological University
Position
Exam Date 2018
City, State karnataka, belagavi


Question Paper

15CV61
Visvesvaraya Technological University, Belagavi
MODEL QUESTION PAPER- 6th Semester B.E (CBCS) CV
Course 15CV61 -Construction Management and Entrepreneurship
Time 3 hours Max Marks 80
Note Answer any FIVE full questions selecting any one full question from each module.
Assume missing data suitably and clearly mention in the answer script about it
Module-1
1a Identify the Stake holders in a construction project and Explain the Roles of
Contractor and PMC Consultants
08
1b Define Lag time and Lead Time in a PND explain with diagram the different
relationship between predecessor and successor activities using this concept
08
OR
2a Explain the Concept of Work break down Structure with an Example 06
2b Using CPM Method determine " Critical activities" and Critical path for the network given
below. What is project duration
10
Module-2
3a List out various Inventory Control Techniques adopted in Material Management and Explain
analysis
08
3b For a typical Project of Cost Rs Cr 900 has its Direct Labour cost of 22% of Gross.
Productive labour cost is 35% of labour Cost. By optimization of Work there was 38%
reduction in Labour non Productivity as compared to earlier. Estimate the total Cost of
Saving in Labour productivity by above process in terms of Rs Cr and in wrt Project Cost
Labour Cost and Productive labour Cost
08
OR
4a List out Factors behind the Selection of Construction equipment's perform assigned tasks Project's need 04
4b An Excavator with a bucket capacity is 1.5 cum and rated horse power is 180HP is used for
excavation of ordinary soil. Following information is available
1. Capital cost of excavator Rs80 lakhs Charged to the project 2.25% per month of
capital cost
2. Employment hrs month 250 hrs ,Technical life 5 yrs salvage value 10% of Capital
Cost
3. Prime mover diesel load factor 0.85 crank case capacity 30 lit. time between oil
change 100 hours.
4. Operational correction factors 0.7 load factor 0.85 bucket swing factor 1.00
bucket fill factor 0.9
5. Operational manpower cost Rs 175 hr
12
6. Time cycle for 1 operation of excavator 45sec for 55 min hour.
7. Routine maintenance and major repair cost 120% of depreciation cost.
8. Diesel rate rs 70 lit and lube rate is rs 200 lit
Estimate
· Hourly production rate of the excavator in cum hr
· Cost of ownership and operation in rs/ hr
· Unit rate of equipment operation for Excavatorin Rs cum.
· Estimate The Number of Excavator needed to do a Job of Earthwork in Sub Grade having
a Compacted Volume Quantity of 70,000 Cum to be executed in 24 days with 10 hrs
working per day.
Determine the number of dumpers required for transportation if average lead from borrow area
to site is 8kms and dumper have a capacity of 12 cum its forward speed is 15 kmph
backward speed is 30 kmph unloading time 4 min repositioning time 2 min.
performance efficiency factor 50min hour time
Module-3
5a Briefly Explain the construction Quality process. 06
5b List out broad principles of quality management systems as outlined under ISO 9000 04
5c Describe safety measures to be adopted while doing Hot Bituminous Works to avoid
accidents
06
OR
6a Define Values Morals and Ethics and List out seven ethical principles applicable to
construction industry
06
6b What is importance of tool box meeting and good house keeping in construction safety
management?
04
6c Explain " Quality Audit and its Process" 06
Module-4
7a Discuss briefly " concept of engineering economic study and its principles" 08
7b What is the Total Capitalized cost of a building which have construction cost Rs
immediately Rs 15000 expenses each year for first 5 yrs and annual year end maintenance
cost of Rs 5000/- plus the expenditure of Rs 35000 at the end of each 10years period for
replacement purpose assume rate of interest 9.5% P.a
08
OR
8a Cash Flow for two projects X Y are given below using annual worth method make a
selection from following alternatives assume min attractive rate of return
End of Year 0 1 2 3 4
PRO X -50000 5000 17500 30000 42500
PROJ Y -50000 40000 15000 15000 15000
10
8b What is present equivalent money value of Rs 5 years from now 5 years
before today take discounting rate 12% compounded quarterly
06
Module-5
9a Define Micro small and medium enterprises list and explain characteristics of MSME 08
9b List and Explain the Different sources of Finance for Entrepreneur 08
OR
10a What id DPR Discuss the guidelines for the preparation of model project report for starting
new venture
08
10b Explain the stages in Entrepreneur entrepreneurial process 08


Other Question Papers

Subjects

  • alternative building materials
  • b.e.
  • biomedical equipments
  • biomedical instrumentation
  • building services - iv
  • building services – ii
  • building services – iv
  • building structures-i
  • clinical instrumentation - ii
  • clinical instrumentation – i
  • construction management and entrepreneurship
  • data structure u sing c+ +
  • design of machine elements
  • design of steel structural elements
  • digital communication
  • dynamics of machinery
  • electrical and electronic measurement
  • electrical estimation and costing
  • energy and environment
  • environmental protection and management
  • finite element method of analysis
  • fundamentals of signals and dsp
  • highway engineering (15cv63)
  • history of architecture
  • history of architecture -v
  • laser physics and non – linear optics
  • machine learning
  • management and economics
  • management and entrepreneurship
  • management and entrepreneurship development
  • management and entrepreneurship development.
  • materials and methods in building construction
  • materials and methods in building construction - vii
  • materials and methods in building construction – v
  • matrix method of structural analysis
  • microcontroller
  • non traditional machining
  • numerical methods and applications (15cv663)
  • operating systems
  • optimization techniques
  • power electronics
  • power system analysis 2
  • power system protection
  • process control systems
  • professional practice i
  • signals and systems
  • sociology and building economics
  • software application lab
  • solid waste management
  • special electrical machines
  • theory of elasticity
  • turbomachines
  • urban design
  • virtual bio-instrumentation
  • vlsi design
  • water resources management
  • water supply and treatment engineering