Question Paper
15CV61
Visvesvaraya Technological University, Belagavi
MODEL QUESTION PAPER
6thSemester B.E (CBCS) CV
Course 15CV61 -Construction Management and Entrepreneurship
Time 3 hours Max Marks 80
Note Answer any FIVE full questions selecting any one full question from each module.
Assume missing data suitably and clearly mention in the answer script about it
Module-1
1a Define Management and List out management functions or process 04
1b Define " Activity Time" Event Time Critical Path and Total Float 08
1c Compute the Project duration of PND given Below
12
18
10
3
A FS=4 B FS= C FS=0 D
1.1
1.2
1.3
1.4
04
OR
2a List out different types of construction organization structure and explain " Matrix
Organization Structure"
08
2b Explain the Concept of Scheduling through " Bar or Gantt chart " and Mile stone
Chart" How Mile stone chart is Converted to Network Diagram
08
Module-2
3a Explain Main Provisions of the Minimum wages act 1948 as amended now) 06
3b A labor gang consisting of 4 Skilled 8 Unskilled and 2 Highly Skilled will do 20 MT of
Rebar Work at Ground Floor in 8 Hrs duration per Day. The building is GF+ 2 Upper floors
and each floor have 1200MT of Bar bending work. The productivity decreases at the rate of
for each floor. The work needs to be completed in 24 days of 8 hours working per day.
Estimate following
· Total team hour required to complete the activity.
· Total number of Labor gangs required to finish the activity.
· Total work force involved
· total man hours and man days required for the activity
· Unit labor Cost for Activity by adopting Per day rate of Rs 750 for Highly Skilled ,Rs 550
for Skilled and Rs 325 for Unskilled workers.
12
OR
4a Define Workers productivity Standard and list out typical factors affecting the
workers production efficiency
06
4b Define " Depreciation" Salvage Value Book Value. Work out Year by year
Depreciation cost and its Book Value using Straight Line Method and Declining
balance method for an Excavator whose purchase Price is Rs 75Lakhs Technical
Life is 5 yrs Salvage value 15% of capital Cost
12
Module-3
5a Explain " Total Quality Management " " Cost of Quality" and " Quality Control" as
applicable to construction
12
5b Describe safety measures to be adopted while doing open excavation of earth and
rock to avoid accidents
06
OR
6a Which are domains of Ethics List out 7 Ethical conduct in compliance with ethical
principles as applicable in construction
06
6b Define " Quality" and Explain " Construction Quality Process" and " Quality
Assurance"
12
Module-4
7a A concrete mixer has the following cash flow details; Initial purchase price
Rs.775000, Annual operating and maintenance cost Rs.50000 Salvage value
Rs.250000, Useful life 10 years In addition one operator is required to operate the
concrete mixer at cost of Rs.50 per hour. The production (preparation) rate of
concrete of the mixer is 0.25m3 per hour. The revenue to be generated from
production of 1m3 of concrete is Rs.2000. The interest rate is 10% per year. How
many „ cum of concrete need to be produced per year so that the revenue generated
break-evens with the expenditure?
08
7b A company offers 12% interest rate on deposit what is the effective rate of interest if
compounded Monthly Quarterly Semi- annually. Also Calculate Nominal
Interest rate if effective rate is 10% p.a compounded semi- annually
08
OR
8a Type A design of a dam costs Rs 50 crore to construct and an expenses of Rs 7.5
crore every year to operate and maintain it. Type B design of the dam on the other
hand would require Rs 75 crore to construct and an annual expenses of Rs 5 crore to
operate and maintain. Both the designs have considered 100ys as design life of dam.
The minimum required rate of return is which design should be given a goahead.
06
8b There are two alternatives for purchasing a concrete mixer. Both the alternatives have
same useful life. The cash flow details of alternatives are as follows;
Alternative-1: Initial purchase cost Rs.3,00,000, Annual operating and
maintenance cost Rs.20,000, Expected salvage value Rs.1,25,000, Useful life 5
years. Annual revenue generated 75000
Alternative-2: Initial purchase cost Rs.2,00,000, Annual operating and
maintenance cost Rs.35,000, Expected salvage value Rs.70,000, Useful life 5
years. Annual revenue generated Rs 50000
Using present worth method, find out which alternative should be selected, if the rate
of interest is 10% per year.
10
Module-5
9a Define entrepreneur explain the functions of an entrepreneur 08
9b Define a Business plan Explain Business Planning Process 08
OR
10a What are various ways of entry into international business 08
10b Write short Notes on TECKSOK KIADB KSSIDC DIC Single
window agency
08
Visvesvaraya Technological University, Belagavi
MODEL QUESTION PAPER
6thSemester B.E (CBCS) CV
Course 15CV61 -Construction Management and Entrepreneurship
Time 3 hours Max Marks 80
Note Answer any FIVE full questions selecting any one full question from each module.
Assume missing data suitably and clearly mention in the answer script about it
Module-1
1a Define Management and List out management functions or process 04
1b Define " Activity Time" Event Time Critical Path and Total Float 08
1c Compute the Project duration of PND given Below
12
18
10
3
A FS=4 B FS= C FS=0 D
1.1
1.2
1.3
1.4
04
OR
2a List out different types of construction organization structure and explain " Matrix
Organization Structure"
08
2b Explain the Concept of Scheduling through " Bar or Gantt chart " and Mile stone
Chart" How Mile stone chart is Converted to Network Diagram
08
Module-2
3a Explain Main Provisions of the Minimum wages act 1948 as amended now) 06
3b A labor gang consisting of 4 Skilled 8 Unskilled and 2 Highly Skilled will do 20 MT of
Rebar Work at Ground Floor in 8 Hrs duration per Day. The building is GF+ 2 Upper floors
and each floor have 1200MT of Bar bending work. The productivity decreases at the rate of
for each floor. The work needs to be completed in 24 days of 8 hours working per day.
Estimate following
· Total team hour required to complete the activity.
· Total number of Labor gangs required to finish the activity.
· Total work force involved
· total man hours and man days required for the activity
· Unit labor Cost for Activity by adopting Per day rate of Rs 750 for Highly Skilled ,Rs 550
for Skilled and Rs 325 for Unskilled workers.
12
OR
4a Define Workers productivity Standard and list out typical factors affecting the
workers production efficiency
06
4b Define " Depreciation" Salvage Value Book Value. Work out Year by year
Depreciation cost and its Book Value using Straight Line Method and Declining
balance method for an Excavator whose purchase Price is Rs 75Lakhs Technical
Life is 5 yrs Salvage value 15% of capital Cost
12
Module-3
5a Explain " Total Quality Management " " Cost of Quality" and " Quality Control" as
applicable to construction
12
5b Describe safety measures to be adopted while doing open excavation of earth and
rock to avoid accidents
06
OR
6a Which are domains of Ethics List out 7 Ethical conduct in compliance with ethical
principles as applicable in construction
06
6b Define " Quality" and Explain " Construction Quality Process" and " Quality
Assurance"
12
Module-4
7a A concrete mixer has the following cash flow details; Initial purchase price
Rs.775000, Annual operating and maintenance cost Rs.50000 Salvage value
Rs.250000, Useful life 10 years In addition one operator is required to operate the
concrete mixer at cost of Rs.50 per hour. The production (preparation) rate of
concrete of the mixer is 0.25m3 per hour. The revenue to be generated from
production of 1m3 of concrete is Rs.2000. The interest rate is 10% per year. How
many „ cum of concrete need to be produced per year so that the revenue generated
break-evens with the expenditure?
08
7b A company offers 12% interest rate on deposit what is the effective rate of interest if
compounded Monthly Quarterly Semi- annually. Also Calculate Nominal
Interest rate if effective rate is 10% p.a compounded semi- annually
08
OR
8a Type A design of a dam costs Rs 50 crore to construct and an expenses of Rs 7.5
crore every year to operate and maintain it. Type B design of the dam on the other
hand would require Rs 75 crore to construct and an annual expenses of Rs 5 crore to
operate and maintain. Both the designs have considered 100ys as design life of dam.
The minimum required rate of return is which design should be given a goahead.
06
8b There are two alternatives for purchasing a concrete mixer. Both the alternatives have
same useful life. The cash flow details of alternatives are as follows;
Alternative-1: Initial purchase cost Rs.3,00,000, Annual operating and
maintenance cost Rs.20,000, Expected salvage value Rs.1,25,000, Useful life 5
years. Annual revenue generated 75000
Alternative-2: Initial purchase cost Rs.2,00,000, Annual operating and
maintenance cost Rs.35,000, Expected salvage value Rs.70,000, Useful life 5
years. Annual revenue generated Rs 50000
Using present worth method, find out which alternative should be selected, if the rate
of interest is 10% per year.
10
Module-5
9a Define entrepreneur explain the functions of an entrepreneur 08
9b Define a Business plan Explain Business Planning Process 08
OR
10a What are various ways of entry into international business 08
10b Write short Notes on TECKSOK KIADB KSSIDC DIC Single
window agency
08
Subjects
- alternative building materials
- b.e.
- biomedical equipments
- biomedical instrumentation
- building services - iv
- building services – ii
- building services – iv
- building structures-i
- clinical instrumentation - ii
- clinical instrumentation – i
- construction management and entrepreneurship
- data structure u sing c+ +
- design of machine elements
- design of steel structural elements
- digital communication
- dynamics of machinery
- electrical and electronic measurement
- electrical estimation and costing
- energy and environment
- environmental protection and management
- finite element method of analysis
- fundamentals of signals and dsp
- highway engineering (15cv63)
- history of architecture
- history of architecture -v
- laser physics and non – linear optics
- machine learning
- management and economics
- management and entrepreneurship
- management and entrepreneurship development
- management and entrepreneurship development.
- materials and methods in building construction
- materials and methods in building construction - vii
- materials and methods in building construction – v
- matrix method of structural analysis
- microcontroller
- non traditional machining
- numerical methods and applications (15cv663)
- operating systems
- optimization techniques
- power electronics
- power system analysis 2
- power system protection
- process control systems
- professional practice i
- signals and systems
- sociology and building economics
- software application lab
- solid waste management
- special electrical machines
- theory of elasticity
- turbomachines
- urban design
- virtual bio-instrumentation
- vlsi design
- water resources management
- water supply and treatment engineering