B5.1-R4 Page 1 of 2 July, 2017
B5.1-R4: SOFTWARE PROJECT MANAGEMENT
491001
NOTE:
Time: 3 Hours Total Marks: 100
1.
What are the characteristics of a good software. Elaborate
What is Personal Software Process? Explain its framework.
What is a Commercial Off the Shelf (COTS) process model? Explain.
How is Function Point Analysis used in Project Planning? Explain.
What is Pareto Analysis technique?
Explain Software Project Scheduling Principles?
Explain Work Breakdown Structure with an example.
2.
Discuss some of the challenges faced in software project management.
Compare the Walston-Felix model with the SEL model on a software development expected to
involve 8 person-years of effort.
Calculate the number of lines of source code that can be produced.
ii) Calculate the duration of the development.
iii) Calculate the productivity in LOC/PY.
iv) Calculate the average manning.
3.
A software development project is planned to cost 95 MY in a period of 1 year and 9 months.
Calculate the peak manning and average rate of software team build up.
What Is Auditing? Discuss three Types of audits? What is the difference between first-party,
second-party, and third-party audits? What are the phases of an audit? What benefits can be
achieved by conducting software audits?
4.
Draw a simple work breakdown structure for the manufacture of a bicycle.
Explain the benefits of using a work breakdown structure.
State three other breakdown structures which can be developed from a WBS.
List different categories of software risks in projects.
5.
Explain the prototyping model with its advantages and disadvantages.
Explain Object-Oriented Analysis, Object-Oriented Design and Object-Oriented Modelling
approaches.
Briefly specify object-oriented metrics that can be used to estimate object oriented software
projects?
1. Answer question 1 and any FOUR from questions 2 to 7.
2. Parts of the same question should be answered together and in the same sequence.
B5.1-R4 Page 2 of 2 July, 2017
6.
Differentiate between Resource Leveling and Resource Smoothing in Project Management?
The following represent activities in a major construction project. Draw the network to represent
this project.
Activity Immediate Predecessor
A
B
C A
D B
E B
F E
G D
H G
What is a Software Management Plan? What are the typical aspects of Software Management
Plan?
7.
Describe alternative methods of software estimation. What are the merits and demerits of
method based on LOC and that based on function points?
What are the three different Project categories in COCOMO model? Explain the basic
COCOMO Model and how estimation of development effort and development time takes place
in three categories?
B5.1-R4: SOFTWARE PROJECT MANAGEMENT
491001
NOTE:
Time: 3 Hours Total Marks: 100
1.
What are the characteristics of a good software. Elaborate
What is Personal Software Process? Explain its framework.
What is a Commercial Off the Shelf (COTS) process model? Explain.
How is Function Point Analysis used in Project Planning? Explain.
What is Pareto Analysis technique?
Explain Software Project Scheduling Principles?
Explain Work Breakdown Structure with an example.
2.
Discuss some of the challenges faced in software project management.
Compare the Walston-Felix model with the SEL model on a software development expected to
involve 8 person-years of effort.
Calculate the number of lines of source code that can be produced.
ii) Calculate the duration of the development.
iii) Calculate the productivity in LOC/PY.
iv) Calculate the average manning.
3.
A software development project is planned to cost 95 MY in a period of 1 year and 9 months.
Calculate the peak manning and average rate of software team build up.
What Is Auditing? Discuss three Types of audits? What is the difference between first-party,
second-party, and third-party audits? What are the phases of an audit? What benefits can be
achieved by conducting software audits?
4.
Draw a simple work breakdown structure for the manufacture of a bicycle.
Explain the benefits of using a work breakdown structure.
State three other breakdown structures which can be developed from a WBS.
List different categories of software risks in projects.
5.
Explain the prototyping model with its advantages and disadvantages.
Explain Object-Oriented Analysis, Object-Oriented Design and Object-Oriented Modelling
approaches.
Briefly specify object-oriented metrics that can be used to estimate object oriented software
projects?
1. Answer question 1 and any FOUR from questions 2 to 7.
2. Parts of the same question should be answered together and in the same sequence.
B5.1-R4 Page 2 of 2 July, 2017
6.
Differentiate between Resource Leveling and Resource Smoothing in Project Management?
The following represent activities in a major construction project. Draw the network to represent
this project.
Activity Immediate Predecessor
A
B
C A
D B
E B
F E
G D
H G
What is a Software Management Plan? What are the typical aspects of Software Management
Plan?
7.
Describe alternative methods of software estimation. What are the merits and demerits of
method based on LOC and that based on function points?
What are the three different Project categories in COCOMO model? Explain the basic
COCOMO Model and how estimation of development effort and development time takes place
in three categories?
Other Question Papers
Departments
- electronics & information technology
Subjects
- accounting & financial management system
- advanced algorithms
- advanced computer graphics
- advanced computer networks
- application of .net technology
- applied operations research
- artificial intelligence & neural networks
- automata theory & compiler design
- basic mathematics
- basics of os, unix & shell programming
- basics of os, unix and shell programming
- computer based statistical & numerical methods
- computer graphics & multimedia
- computer system architecture
- cyber forensic & law
- data communication and network technologies
- data communication and network technologies
- data network and management
- data structure through c++
- data structure through java
- data structures through ‘c++’
- data warehouse and data mining
- data warehousing and data mining
- digital image processing
- digital image processing and computer visio
- digital signal processing
- discrete structures
- e-business
- elements of mathematical sciences
- embedded systems
- graphics and visualisation
- image processing and computer vision
- information security
- information storage & management
- internet technology and web design
- internet technology and web design
- internet technology and web services
- introduction to database management system
- introduction to dbms
- introduction to ict resources
- introduction to multimedia
- introduction to object oriented programming through java
- introduction to object-oriented programming through java
- it tools and business system
- it tools and business systems
- machine learning
- management fundamentals & information systems
- mathematical methods for computing
- mobile computing
- multimedia systems
- multimedia systems
- network management & information security
- object oriented database management systems
- operating system
- operating systems
- parallel computing
- professional & business communication
- programming and problem solving through ‘c’ language
- programming and problem solving through ‘c’ language
- project management
- soft computing
- software engineering and case tools
- software project management
- software systems
- software testing and quality management
- software testing and quality management
- structured system analysis & design
- structured system analysis and design
- system modeling & computer simulation
- visual programming
- wireless & mobile communication