B5.1-R4 Page 1 of 2 January, 2017
B5.1-R4: SOFTWARE PROJECT MANAGEMENT
NOTE:
Time: 3 Hours Total Marks: 100
1.
What is project management? What are the activities of software project management?
What is work breakdown structure Mention five levels of WBS
Explain 'throwaway' prototype and 'evolutionary' prototype models. Compare advantages and
disadvantages of each.
Define development costs? What are the steps in cost-benefit analysis?
Define risk analysis and risk monitoring? What things are to be considered in risk management?
What is function point? Mention its importance. Write any three advantages of function point
analysis.
What are the issues that get addressed during project closure?
2.
Net Present Value measures the total value of an investment over its lifetime. Why is it useful to
know the Net Present Value of a proposed software project? How would you calculate the Net
Present Value of a proposed project?
What do you understand by Software development life cycle? Draw a diagram and explain
briefly major activities or phases in it.
3.
What do you understand by software project planning? List the problems faced by software
project manager in developing a high quality software project.
List at least six reasons for software project delays? How unrealistic deadlines are handled?
List four reasons why it is difficult to improve software process.
4.
Compare the basic COCOMO model with intermediate and detailed COCOMO model.
Explain what is meant by stakeholder management and describe how the project manager
ensures stakeholder co-operation.
Explain span and average span size for a program.
5. Describe the following concepts with the help of relevant examples:
Aids for Risk Identification
ii) Risk Components and drivers
iii) Risk Prioritization
1. Answer question 1 and any FOUR from questions 2 to 7.
2. Parts of the same question should be answered together and in the same
sequence.
B5.1-R4 Page 2 of 2 January, 2017
6.
Determine network diagram; ii) critical path; iii) ES, EF, LS and LF; iv) free slack for each
activity for the project parameters given below.
Task Number Description Duration (days) Dependent on Tasks
T1 Specification 15
T2 Design Database 45 T1
T3 Design GUI 30 T1
T4 Code database 105 T2
T5 Code GUI part 45 T3
T6 Integrate and Test 120 T4 and T5
T7 Write user manual 60 T1
How does the risk factor affect the spiral model of software development?
7.
What are the challenges in developing web based projects. Is there any disadvantage of such
projects? If yes, explain briefly.
Write the difference between program managers and project managers.
B5.1-R4: SOFTWARE PROJECT MANAGEMENT
NOTE:
Time: 3 Hours Total Marks: 100
1.
What is project management? What are the activities of software project management?
What is work breakdown structure Mention five levels of WBS
Explain 'throwaway' prototype and 'evolutionary' prototype models. Compare advantages and
disadvantages of each.
Define development costs? What are the steps in cost-benefit analysis?
Define risk analysis and risk monitoring? What things are to be considered in risk management?
What is function point? Mention its importance. Write any three advantages of function point
analysis.
What are the issues that get addressed during project closure?
2.
Net Present Value measures the total value of an investment over its lifetime. Why is it useful to
know the Net Present Value of a proposed software project? How would you calculate the Net
Present Value of a proposed project?
What do you understand by Software development life cycle? Draw a diagram and explain
briefly major activities or phases in it.
3.
What do you understand by software project planning? List the problems faced by software
project manager in developing a high quality software project.
List at least six reasons for software project delays? How unrealistic deadlines are handled?
List four reasons why it is difficult to improve software process.
4.
Compare the basic COCOMO model with intermediate and detailed COCOMO model.
Explain what is meant by stakeholder management and describe how the project manager
ensures stakeholder co-operation.
Explain span and average span size for a program.
5. Describe the following concepts with the help of relevant examples:
Aids for Risk Identification
ii) Risk Components and drivers
iii) Risk Prioritization
1. Answer question 1 and any FOUR from questions 2 to 7.
2. Parts of the same question should be answered together and in the same
sequence.
B5.1-R4 Page 2 of 2 January, 2017
6.
Determine network diagram; ii) critical path; iii) ES, EF, LS and LF; iv) free slack for each
activity for the project parameters given below.
Task Number Description Duration (days) Dependent on Tasks
T1 Specification 15
T2 Design Database 45 T1
T3 Design GUI 30 T1
T4 Code database 105 T2
T5 Code GUI part 45 T3
T6 Integrate and Test 120 T4 and T5
T7 Write user manual 60 T1
How does the risk factor affect the spiral model of software development?
7.
What are the challenges in developing web based projects. Is there any disadvantage of such
projects? If yes, explain briefly.
Write the difference between program managers and project managers.
Other Question Papers
Departments
- electronics & information technology
Subjects
- accounting & financial management system
- advanced algorithms
- advanced computer graphics
- advanced computer networks
- application of .net technology
- applied operations research
- artificial intelligence & neural networks
- automata theory & compiler design
- basic mathematics
- basics of os, unix & shell programming
- basics of os, unix and shell programming
- computer based statistical & numerical methods
- computer graphics & multimedia
- computer system architecture
- cyber forensic & law
- data communication and network technologies
- data communication and network technologies
- data network and management
- data structure through c++
- data structure through java
- data structures through ‘c++’
- data warehouse and data mining
- data warehousing and data mining
- digital image processing
- digital image processing and computer visio
- digital signal processing
- discrete structures
- e-business
- elements of mathematical sciences
- embedded systems
- graphics and visualisation
- image processing and computer vision
- information security
- information storage & management
- internet technology and web design
- internet technology and web design
- internet technology and web services
- introduction to database management system
- introduction to dbms
- introduction to ict resources
- introduction to multimedia
- introduction to object oriented programming through java
- introduction to object-oriented programming through java
- it tools and business system
- it tools and business systems
- machine learning
- management fundamentals & information systems
- mathematical methods for computing
- mobile computing
- multimedia systems
- multimedia systems
- network management & information security
- object oriented database management systems
- operating system
- operating systems
- parallel computing
- professional & business communication
- programming and problem solving through ‘c’ language
- programming and problem solving through ‘c’ language
- project management
- soft computing
- software engineering and case tools
- software project management
- software systems
- software testing and quality management
- software testing and quality management
- structured system analysis & design
- structured system analysis and design
- system modeling & computer simulation
- visual programming
- wireless & mobile communication