1
Seat No.: Enrolment
GUJARAT TECHNOLOGICAL UNIVERSITY
MBA SEMESTER 4 EXAMINATION SUMMER 2019
Subject Code: 2840006 Date:03/05/2019
Subject Name: PROJECT MANAGEMENT
Time: 10:30 AM To 01:30 PM Total Marks: 70
Instructions:
1. Attempt all questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.
Q.1
Multiple Choice Questions:
06
1.
Resources refers to
a. Manpower
b. Machinery
c. Materials
d. All of the above
2.
In the stage of the project life cycle, a major portion of the physical project work performed
a. Identifying
b. Defining
c. Execution
d. Controlling
3.
Which of the following choices is NOT one of the driving forces behind the increasing demand for project management
a. Compression of product lifecycle
b. Knowledge explosion
c. Declining need for product customization
d. More sustainable business practices
4.
Which dimension of project management centers on creating a temporary social system within a larger organizational environment that combines the talents of a divergent set of professionals working to complete the project
a. Communication
b. Sociocultural
c. Social
d. Technical
5.
Which of the following elements is not normally common in projects?
a. An objective
b. Uniqueness
c. Uncertainty
d. No defined end point
6.
The Critical Path is an activity (or series of activities) that if delayed will delay the whole project.
a. True
b. False
Q.1
Explain the following terms:
i. Perpetual closure
ii. Pre-feasibility and feasibility studies
iii. Project Finance
iv. PERT
04
Q.1
Briefly describe the role of SIDBI towards project financing.
04
Q.2
Depict your understanding for "Work Breakdown Structure". Develop WBS for a project of making an electric car suitable for Indian environment.
07
Discuss the trade-off between the activity duration and the associated cost. Why is it said that all such activity duration reduction may not be desirable? Elaborate.
07
2
OR
What is the meaning of Resource Constrained Project? Explain the types of Resource Constraints.
07
Q.3
Some of the organizations outsource their projects, due to the shortage of resources and expertise. Which are the key points that an organization should consider while outsourcing?
07
Depict your understanding for negotiation in project partnering.
07
OR
Q.3
Suppose you are appointed as project manager to build a high-rise building with a financial limit of Rs. 20 Crores and within two year time limit. Assume other necessary things and develop the scope statement including all the elements.
07
Compare and Contrast Preference Shares and Debentures as a source of long term fund.
07
Q.4
Explain different three types of matrix structures for organizing a project.
07
Discuss various types of project terminations with examples.
07
OR
Q.4
Write a note on project team pitfalls.
07
Why team work is important in Project Management? Describe the Five Stage Team Development Model.
07
3
Q.5
Global Green Books Publishing was started two years ago by two friends, Jim King and Brad Mount, who met in college while studying in Philadelphia, USA. In the new business Jim focused on editing, sales and marketing while Brad Mount did the electronic assembly and publishing of books for Global Green Books. Their business was successful and profitable in the first two years, largely due to contracts from two big businesses.
In their third year they got very busy thanks to their third major customer, a local college that needed customized eBooks. They hired several part time employees to help them with their publishing business.
But by the end of third year of operation, Global Green Books started experiencing critical problems. They were:
unable to leverage all the new employees effectively
unable to deliver eBooks to their customers on schedule
unable to provide quality texts—time and money was being spent fixing defects in their products
Unable to control costs—their business was not profitable in the third year.
Global Green Books saw a significant rise in issues, a lot of unpleasant "surprises" were cropping up; business was down as new resources were hired, also some of the projects were poorly estimated. The local university was unhappy as their eBook products reached campus late for use by professors and student. In some cases, the books were a week or two late. Since the courses must start on schedule and students need their books at the beginning of their courses, the new lucrative college customer was unhappy.
One of the new part-time employees hired by Jim and Brad, Samantha, had taken a project management course at college. Samantha was excited about the discipline of project management and had intentionally selected a job with Global Green Books Publishing as she saw an opportunity to polish her project management skills.
One fine day, Jim invited Samantha, for a lunch meeting. He was aware that Samantha was familiar with project management, and wanted to hear what she had to say about the problems he and Brad were facing. Over lunch he questioned why their small business which had operated and implemented projects so successfully over the first two years was being challenged significantly now. He specifically listed the problems they were facing and asked for input to solve them.
Samantha asked for more time to research all the issues but noted that Global Green Books, while being innovative, completed projects without a roadmap or a project plan and lacked a disciplined approach to project management. She noted that Jim and Brad did not use any project software for scheduling and they did not use tools or techniques to estimate, budget or to communicate with stakeholders. Finally, they had no processes in place to manage project risks and quality.
Impressed with this and other conversations, Jim King asked Samantha if she would consider joining them as a project associate or project manager on a full-time basis to help them introduce project management practices and help them tide over their current crisis.
Samantha accepted the offer! She has several key skills—she is an excellent communicator with very good interpersonal skills and detail-oriented. Within the first three months in her new role as PM, she introduced formal project management processes, created a PM manual and trained the employees to get the work done well.
Within nine months Samantha had fully turned things around. Due to proactive risk analysis and risk response planning, surprises and issues reduced. Communication with stakeholders was enhanced.
Brad and Jim noted that the company was delivering projects on schedule, the quality processes worked—and customers were happy with the products!
14
4
Comment on the following aspects of the case study:
Why did Global Green Books Publishing struggle?
What were the specific PM solutions that were introduced by Samantha that worked?
What kind of suggestions would you give to Brad and Jim if you were the
PM?
OR
Q.5
A project consists of nine activities whose time estimates (in weeks) and other characteristics are given below:
Activity
Preceding Activity(ies)
Time estimates
Most Optimistic
Most Likely
Most Pessimistic
A
2
4
6
B
6
6
6
C
6
12
24
D
A
2
5
8
E
A
11
14
23
F
B,D
8
10
12
G
B,D
3
6
9
H
C,F
9
15
27
I
E
4
10
16
i. Show the PERT network for the project.
ii. Identify the critical activities
iii. What are the expected project completion time and its variance?
iv. What is the probability of completing the project one week before the expected time?
14
Seat No.: Enrolment
GUJARAT TECHNOLOGICAL UNIVERSITY
MBA SEMESTER 4 EXAMINATION SUMMER 2019
Subject Code: 2840006 Date:03/05/2019
Subject Name: PROJECT MANAGEMENT
Time: 10:30 AM To 01:30 PM Total Marks: 70
Instructions:
1. Attempt all questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.
Q.1
Multiple Choice Questions:
06
1.
Resources refers to
a. Manpower
b. Machinery
c. Materials
d. All of the above
2.
In the stage of the project life cycle, a major portion of the physical project work performed
a. Identifying
b. Defining
c. Execution
d. Controlling
3.
Which of the following choices is NOT one of the driving forces behind the increasing demand for project management
a. Compression of product lifecycle
b. Knowledge explosion
c. Declining need for product customization
d. More sustainable business practices
4.
Which dimension of project management centers on creating a temporary social system within a larger organizational environment that combines the talents of a divergent set of professionals working to complete the project
a. Communication
b. Sociocultural
c. Social
d. Technical
5.
Which of the following elements is not normally common in projects?
a. An objective
b. Uniqueness
c. Uncertainty
d. No defined end point
6.
The Critical Path is an activity (or series of activities) that if delayed will delay the whole project.
a. True
b. False
Q.1
Explain the following terms:
i. Perpetual closure
ii. Pre-feasibility and feasibility studies
iii. Project Finance
iv. PERT
04
Q.1
Briefly describe the role of SIDBI towards project financing.
04
Q.2
Depict your understanding for "Work Breakdown Structure". Develop WBS for a project of making an electric car suitable for Indian environment.
07
Discuss the trade-off between the activity duration and the associated cost. Why is it said that all such activity duration reduction may not be desirable? Elaborate.
07
2
OR
What is the meaning of Resource Constrained Project? Explain the types of Resource Constraints.
07
Q.3
Some of the organizations outsource their projects, due to the shortage of resources and expertise. Which are the key points that an organization should consider while outsourcing?
07
Depict your understanding for negotiation in project partnering.
07
OR
Q.3
Suppose you are appointed as project manager to build a high-rise building with a financial limit of Rs. 20 Crores and within two year time limit. Assume other necessary things and develop the scope statement including all the elements.
07
Compare and Contrast Preference Shares and Debentures as a source of long term fund.
07
Q.4
Explain different three types of matrix structures for organizing a project.
07
Discuss various types of project terminations with examples.
07
OR
Q.4
Write a note on project team pitfalls.
07
Why team work is important in Project Management? Describe the Five Stage Team Development Model.
07
3
Q.5
Global Green Books Publishing was started two years ago by two friends, Jim King and Brad Mount, who met in college while studying in Philadelphia, USA. In the new business Jim focused on editing, sales and marketing while Brad Mount did the electronic assembly and publishing of books for Global Green Books. Their business was successful and profitable in the first two years, largely due to contracts from two big businesses.
In their third year they got very busy thanks to their third major customer, a local college that needed customized eBooks. They hired several part time employees to help them with their publishing business.
But by the end of third year of operation, Global Green Books started experiencing critical problems. They were:
unable to leverage all the new employees effectively
unable to deliver eBooks to their customers on schedule
unable to provide quality texts—time and money was being spent fixing defects in their products
Unable to control costs—their business was not profitable in the third year.
Global Green Books saw a significant rise in issues, a lot of unpleasant "surprises" were cropping up; business was down as new resources were hired, also some of the projects were poorly estimated. The local university was unhappy as their eBook products reached campus late for use by professors and student. In some cases, the books were a week or two late. Since the courses must start on schedule and students need their books at the beginning of their courses, the new lucrative college customer was unhappy.
One of the new part-time employees hired by Jim and Brad, Samantha, had taken a project management course at college. Samantha was excited about the discipline of project management and had intentionally selected a job with Global Green Books Publishing as she saw an opportunity to polish her project management skills.
One fine day, Jim invited Samantha, for a lunch meeting. He was aware that Samantha was familiar with project management, and wanted to hear what she had to say about the problems he and Brad were facing. Over lunch he questioned why their small business which had operated and implemented projects so successfully over the first two years was being challenged significantly now. He specifically listed the problems they were facing and asked for input to solve them.
Samantha asked for more time to research all the issues but noted that Global Green Books, while being innovative, completed projects without a roadmap or a project plan and lacked a disciplined approach to project management. She noted that Jim and Brad did not use any project software for scheduling and they did not use tools or techniques to estimate, budget or to communicate with stakeholders. Finally, they had no processes in place to manage project risks and quality.
Impressed with this and other conversations, Jim King asked Samantha if she would consider joining them as a project associate or project manager on a full-time basis to help them introduce project management practices and help them tide over their current crisis.
Samantha accepted the offer! She has several key skills—she is an excellent communicator with very good interpersonal skills and detail-oriented. Within the first three months in her new role as PM, she introduced formal project management processes, created a PM manual and trained the employees to get the work done well.
Within nine months Samantha had fully turned things around. Due to proactive risk analysis and risk response planning, surprises and issues reduced. Communication with stakeholders was enhanced.
Brad and Jim noted that the company was delivering projects on schedule, the quality processes worked—and customers were happy with the products!
14
4
Comment on the following aspects of the case study:
Why did Global Green Books Publishing struggle?
What were the specific PM solutions that were introduced by Samantha that worked?
What kind of suggestions would you give to Brad and Jim if you were the
PM?
OR
Q.5
A project consists of nine activities whose time estimates (in weeks) and other characteristics are given below:
Activity
Preceding Activity(ies)
Time estimates
Most Optimistic
Most Likely
Most Pessimistic
A
2
4
6
B
6
6
6
C
6
12
24
D
A
2
5
8
E
A
11
14
23
F
B,D
8
10
12
G
B,D
3
6
9
H
C,F
9
15
27
I
E
4
10
16
i. Show the PERT network for the project.
ii. Identify the critical activities
iii. What are the expected project completion time and its variance?
iv. What is the probability of completing the project one week before the expected time?
14
Other Question Papers
Subjects
- accounting for managers
- accounting for managers (afm)
- advance marketing management
- applied pharmaceutics
- b2b marketing
- banking and insurance
- banking and insurance -ii
- brand marketing
- business analytics (ba)
- business communication
- business english (be)
- business environment
- business ethics
- business ethics and corporate governance (becg)
- business law for managers
- business mathematics
- business process reengineering
- business process reengineering (bpr)
- business statistics
- business statistics (bs)
- business structure and management
- business structure and process
- change management & organization development
- change management and organizational development
- company law
- compensation management
- computer applications
- constitution of india
- consumer behavior (cb)
- consumer behaviour
- cooperative management
- corporate accounting (ca)
- corporate restructuring
- corporate tax planning
- corporate taxation (ct)
- corporate taxation and financial planning (ct & fp)
- cost & management accounting (cma)
- cost and management accounting
- counseling skills for managers
- creativity and innovation
- creativity, incubation and innovation (cii)
- cross continent business philosophy
- cyber security and it governance (csitg)
- database management
- designing of operations system (dos)
- development of human skills
- digital marketing
- e-commerce
- ecological management & business
- economics for managers (efm)
- effective communication skills
- elements of direct & indirect taxes
- elements of financial accounting
- english language
- enterprise resource planning
- entrepreneurial finance (ef)
- entrepreneurship
- environment for business
- environment management
- export – import policy, procedure documentation
- export-import policy procedures & documentation
- export-import procedures
- family business management
- financial accounting
- financial management
- financial planning
- foreign exchange management
- foreign language-french
- french (foreign language)
- fundamentals of information technology
- fundamentals of marketing (fom)
- gandhian philosophy for managing business (gpmb)
- german (foreign language)
- global human resource management (ghrm)
- healthcare and hospital management
- human resource development
- human resource management
- human resource management.
- human skills
- human values & business ethics (hvbe)
- import export procedures
- income tax (it)
- indian economy
- indian ethos & human quality development
- information system audit and control
- information systems
- information technology and global business
- integrated marketing communication
- integrated marketing communication (imc)
- intellectual property rights
- international accounting practice
- international business
- international business (ib)
- international commercial law (icl)
- international economic environment (iee)
- international economics (ie)
- international finance
- international financial management (ifm)
- international human resource management
- international human resource management (ihrm)
- international marketing
- international supply chain management
- inventory management, material planning and management
- inventory management, materials planning and management
- investment banking (ib)
- labor law
- leadership
- legal aspects business
- legal aspects of business
- legal aspects of business (lab)
- macro economics (me)
- management accounting
- management control system
- management control systems
- management information system
- management of cooperatives
- management of financial planning (mfp)
- management of financial services (mfs)
- management of industrial relation and labour law
- management of industrial relations and labour laws (mir & ll)
- management principles
- managerial communication
- managerial communication (mc)
- managerial economics
- managerial economics(me)
- managing digital innovation and transformation (mdit)
- marketing management
- marketing research (mr)
- material management
- mergers and acquisitions
- micro economics
- micro small and medium enterprise
- multicultural organizational behavior (mob)
- new entrepreneurship & innovation management
- new venture creation
- operation management
- organisational dynamics
- organizational behavior
- organizational behaviour
- performance management (pm)
- principles of management (pm)
- product & brand management (pbm)
- product and brand management
- product design and development
- production & operations management (pom)
- production and operations management
- production management
- project management
- project management for entrepreneurs
- public relation management
- quantitative analysis - ii
- quantitative analysis (qa)
- quantitative analysis-i
- relational database management system (rdbms)
- research methodology
- research methodology (rm)
- retailing - ii
- retailing and franchising (rf)
- risk management
- rural marketing
- sales & distribution management
- sales and distribution management (sdm)
- security analysis & portfolio management
- security analysis & portfolio management (sapm)
- service marketing
- services and relationship marketing (srm)
- social entrepreneurship
- social media analytics (sma)
- strategic financial management
- strategic financial management (sfm)
- strategic human resource management
- strategic information technology management
- strategic management
- supply chain & logistics management
- supply chain and logistics management
- supply chain management
- supply chain management (scm)
- system analysis and design
- system analysis and design(sa&d)
- talent management
- technology and business
- technology management
- total quality management and world class manufacturing excellence (tqmwcme)
- tourism and hospitality management (thm)
- wto multilateral trading system and it’s impact on business
- wto multilateral trading system and its impact on business(wmts-i)