Seat No.: Enrolment
GUJARAT TECHNOLOGICAL UNIVERSITY
BPLAN SEMESTER- II- EXAMINATION WINTER 2017
Subject Code: 1025503 Date: 30/12/17
Subject Name: SPECIFICATIONS, ESTIMATION AND VALUATION
Time: 02:30pm to 04:30pm Total Marks: 50
Instructions:
1. Attempt all questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.
4. Scientific calculator is allowed.
Q.1 Discuss the Advantages and Disadvantages of open specifications. 05
Q.2 Explain rate analysis. 05
Q.3 What are objects of Specifications? 05
OR
Write notes on different principles of writing a specification.
Q.4 What are the different types and methods of estimates? 05
Q. 5 Explain valuation? 03
Q.6 There is a project which shall be completed 5 years. The expected cost is Rs.500,000. What should be the savings done annually to have a sum of Rs. 500,000 after 5 years, at 20% interest? 06
Q. 7 What are the Legal, fiscal and administrative measures of land value. 05
Q.8 What can be the total sum if a project is completed after 5 years with an initial investment of Rs.20000 at 10% interest rate. 06
Q.9 Prepare detailed estimate and BOQ for WBM road. 10
(You are free to assume rates of all items)
GUJARAT TECHNOLOGICAL UNIVERSITY
BPLAN SEMESTER- II- EXAMINATION WINTER 2017
Subject Code: 1025503 Date: 30/12/17
Subject Name: SPECIFICATIONS, ESTIMATION AND VALUATION
Time: 02:30pm to 04:30pm Total Marks: 50
Instructions:
1. Attempt all questions.
2. Make suitable assumptions wherever necessary.
3. Figures to the right indicate full marks.
4. Scientific calculator is allowed.
Q.1 Discuss the Advantages and Disadvantages of open specifications. 05
Q.2 Explain rate analysis. 05
Q.3 What are objects of Specifications? 05
OR
Write notes on different principles of writing a specification.
Q.4 What are the different types and methods of estimates? 05
Q. 5 Explain valuation? 03
Q.6 There is a project which shall be completed 5 years. The expected cost is Rs.500,000. What should be the savings done annually to have a sum of Rs. 500,000 after 5 years, at 20% interest? 06
Q. 7 What are the Legal, fiscal and administrative measures of land value. 05
Q.8 What can be the total sum if a project is completed after 5 years with an initial investment of Rs.20000 at 10% interest rate. 06
Q.9 Prepare detailed estimate and BOQ for WBM road. 10
(You are free to assume rates of all items)
Other Question Papers
Subjects
- advance remote sensing
- demography and urbanization
- disaster risk mitigation & management
- ecology and environmental management
- elements of economics
- evolution of aesthetics, culture and technology
- geo-informatics for planning
- gis for planning
- housing and community planning
- introduction to regional planning
- introduction to urban design
- land development
- landscape planning and design
- mass transportation
- materials and principles of construction
- metropolitan planning, development & management
- pharmaceutics-i
- planning and management of informal sector
- planning and management of utilities and services
- planning legislation
- planning practice - i
- planning theory - i
- planning theory – ii
- professional practice and ethics
- project formulation, appraisal and management
- real estate planning and management
- rural development & management
- settlement geography
- settlement sociology
- specifications, estimation and valuation
- statistical and quantitative methods in planning - ii
- surveying & photogrammetry
- sustainable urban development
- techniques of planning - i
- traffic and transportation planning-ii
- urban and rural governance
- urban finance
- urban management-i
- urban renewal and conservation