Fourth Year B. Arch. EXAMINATION, 2018
QUANTITY SURVEYING AND ESTIMATING
(2008 PATTERN)
Time Three Hours Maximum Marks 100
N.B. All questions are compulsory.
(ii Answers to the two sections MUST be written in separate
answer-books.
(iii Neat sketches must be drawn wherever necessary.
Figures to the right indicate full marks
Assume suitable data wherever necessary.
Section I
1. Work out quantities for the following items of work based on
the details given in the accompanying diagram (Fig.1)
(any eight)
1. P.C.C. 1 4 8 below footing
2. R.C.C. Beams in 1 2 4
3. Dado tiles only for Bath and WC up to 2.1 m height
4. Windows and Ventilators
P.T.O.
[5357]-43 2
5. RCC Footings 1 2 4
6. Skirting in Bed 100 wide
7. Internal Plaster for walls and ceiling Kitchen only
8. Doors
9. RCC 2 columns in superstructure from FFL to FFL
(FFL-finished floor level)
10. Flooring in Bath and WC.
2. State the unit of measurement as per IS Code 1200 (any ten)
1. Excavation in hard murum
2. External Plastering
3. R.C.C. Lintel in
4. Aluminium Windows
5. Vitrified Tiled Flooring
6. M.S Grill
7. WC in toilet
8. G. I. Pipe 50 mm dia.
9. White Wash
10. 15 Amp. Electrical PowerPoint
11. Chain-link Fencing
12. Bib-Cock.
[5357]-43 3 P.T.O.
Section II
3. Write short notes on (any two)
1. Work Charged Establishment
2. Schedule of rates
3. Rate Analysis.
4. Prepare rate analysis for unit quantity (any three)
1. PCC at Plinth level
2. 230 mm Brick Masonry in 1:4 cement mortar
3. 20 mm thick Cement Plaster in 1:6 cement mortar
4. R.C.C. work in Slab
Material rates
Stone 1500/- per cum
Cement per bag
Sand 4000/- per cum
Aggregate per cum
Bricks per Number
Labour rates
P.C.C. Work per cum
R.C.C. Work per cum
Brick Masonry Work 6,000 per cum
Cement Plaster per sqm
[5357]-43 4
5. Prepare indent of material for the following (any three)
1. P.C.C. at plinth level in for 137 cum
2. 20 mm thick cement plaster in 1:4 mortar for 250.0 sq.m
3. 230 mm thick BB Masonry in 1:4 cement mortar for 368 cum
4. R.C.C. lintels in for 18 cum.
6. Explain in detail the following (any two)
1. Describe any two items as Bill of Quantities for Q. 1 A
2. Explain types of estimates (any two)
3. Explain the long wall and short wall method in quantity
calculation.
QUANTITY SURVEYING AND ESTIMATING
(2008 PATTERN)
Time Three Hours Maximum Marks 100
N.B. All questions are compulsory.
(ii Answers to the two sections MUST be written in separate
answer-books.
(iii Neat sketches must be drawn wherever necessary.
Figures to the right indicate full marks
Assume suitable data wherever necessary.
Section I
1. Work out quantities for the following items of work based on
the details given in the accompanying diagram (Fig.1)
(any eight)
1. P.C.C. 1 4 8 below footing
2. R.C.C. Beams in 1 2 4
3. Dado tiles only for Bath and WC up to 2.1 m height
4. Windows and Ventilators
P.T.O.
[5357]-43 2
5. RCC Footings 1 2 4
6. Skirting in Bed 100 wide
7. Internal Plaster for walls and ceiling Kitchen only
8. Doors
9. RCC 2 columns in superstructure from FFL to FFL
(FFL-finished floor level)
10. Flooring in Bath and WC.
2. State the unit of measurement as per IS Code 1200 (any ten)
1. Excavation in hard murum
2. External Plastering
3. R.C.C. Lintel in
4. Aluminium Windows
5. Vitrified Tiled Flooring
6. M.S Grill
7. WC in toilet
8. G. I. Pipe 50 mm dia.
9. White Wash
10. 15 Amp. Electrical PowerPoint
11. Chain-link Fencing
12. Bib-Cock.
[5357]-43 3 P.T.O.
Section II
3. Write short notes on (any two)
1. Work Charged Establishment
2. Schedule of rates
3. Rate Analysis.
4. Prepare rate analysis for unit quantity (any three)
1. PCC at Plinth level
2. 230 mm Brick Masonry in 1:4 cement mortar
3. 20 mm thick Cement Plaster in 1:6 cement mortar
4. R.C.C. work in Slab
Material rates
Stone 1500/- per cum
Cement per bag
Sand 4000/- per cum
Aggregate per cum
Bricks per Number
Labour rates
P.C.C. Work per cum
R.C.C. Work per cum
Brick Masonry Work 6,000 per cum
Cement Plaster per sqm
[5357]-43 4
5. Prepare indent of material for the following (any three)
1. P.C.C. at plinth level in for 137 cum
2. 20 mm thick cement plaster in 1:4 mortar for 250.0 sq.m
3. 230 mm thick BB Masonry in 1:4 cement mortar for 368 cum
4. R.C.C. lintels in for 18 cum.
6. Explain in detail the following (any two)
1. Describe any two items as Bill of Quantities for Q. 1 A
2. Explain types of estimates (any two)
3. Explain the long wall and short wall method in quantity
calculation.
Other Question Papers
Subjects
- architectural design
- architectural design—iii
- building services—i
- building services—ii
- building technology and materials
- professional practice
- quantity surveying and estimating
- specification writing
- theory of structures
- theory of structures—iii
- town planning