Fourth Year B. Arch. EXAMINATION, 2018
PROFESSIONAL PRACTICE
(2008 BRIDGE PATTERN)
Time Three Hours Maximum Marks 100
N.B. Answers to the two Sections I and II must be written
on separate answer-books.
(ii Answers to Question No. 1 from Section I and Question
No. 6 from Section II are compulsory.
(iii Attempt any two out of the remaining questions in each
Section.
Figures in brackets to the right indicate full marks.
Section-I
1. Describe in detail typical setup of a medium scale professional office
of an Architect, also explaining the role responsibilities of the
Principal architect in his office.
Answer any two of the following
2. What is the role of Council of Architecture in the profession
education of Architecture. Also explain the eligibility and procedure
for registration with the Council of Architecture.
P.T.O.
[5357]-402 2
3. Write short notes on (any marks each)
Code of Conduct for Architects
Role of Allied consultants in a project
Rules of Advertisement prescribed by COA
Proprietary practice in Architecture
Architects agreement with client
Architects responsibility towards society.
4. What do you know about the Indian Institute of Architects Give
its history in brief and its role and activities as a professional organization
of Architects.
5. Write a comprehensive note on ARCHITECTURAL COMPETITIONS,
giving the types and procedures, advantages and disadvantages if
any.
Section II
6. What are the advantages and disadvantages of the Tendering
system Write a note on Types of Tenders Systems of
Tendering.
Answer any two of the following
7. Explain the importance of Contract in a Construction project. Also
explain, the exact role of Architect in preparing implementing
the contract document through articles of agreement.
[5357]-402 3 P.T.O.
8. Write short notes on (any marks each)
Virtual completion certificate
Site visit report
Tender Notice
Liquidated damages
Sentimental value
Demolition tender.
9. What is the process of Arbitration State advantages of Arbitration
vis a vis other methods of settling disputes.
10. Explain the salient differences between the following (Any
Earnest money deposit Security deposit.
Cost, Price and Value
Arbitrator and Umpire
Defects Liability Period and Extended Period
Bonus clause and Penalty clause
Appointed contractor nominated sub contractor.



Other Question Papers

Subjects

  • architectural design
  • architectural design—iii
  • building services—i
  • building services—ii
  • building technology and materials
  • professional practice
  • quantity surveying and estimating
  • specification writing
  • theory of structures
  • theory of structures—iii
  • town planning